BUILDING CONSTRUCTION DETAILS
For any questions or concerns please contact the Office of Campus Planning & Facilities at campus.facilities@lehman.cuny.edu or 718-960-8226.
Shuster Hall Library Old Gym Gillet Hall Carman Hall Music Building Campus Bridge Davis Hall
Shuster Hall
Window Replacement (Estimated Construction Time)
UPDATE: Work on the window replacements for Shuster Hall is currently delayed. Restoration work on other exterior elements of Shuster Hall continues. A return date for the third floor is not currently known.
- Third Floor (10/10/25 – 11/23/25)
- Basement (Construction Start Delayed)
- Second Floor (Construction Start Delayed)
- First Floor (Construction Start Delayed)
Shuster Hall |
||||
|---|---|---|---|---|
Window Replacement |
||||
| Oct-25 | Nov-25 | Dec-25 | Jan-26 | Feb-26 |
| Third Floor | ||||
| Basement - Construction Start Delayed | ||||
| Second Floor - Construction Start Delayed | ||||
| First Floor - Construction Start Delayed | ||||
Temporary Office Locations beginning September 29, 2025
Please note: The Bursar’s Office (032) and Print Shop (056) will remain open and in Shuster Hall for the duration of the construction.
- Office of the President - Music 313
- Office of the Provost - Old Gym Former Bookstore - First Floor
- Office of the Vice President for Administration and Finance - Shuster 012
- Office of the Vice President for Enrollment Management - Shuster 152
- Institutional Advancement – Old Gym Former Bookstore – Basement & Balcony
- Academic Personnel - Old Gym Former Bookstore - First Floor
- Strategic Planning, Assessment & Institutional Research - First Floor
- Campus Planning & Facilities - Old Gym Former Bookstore - Balcony
- ORACLE - Fully Remote
HVAC (Air Conditioning) Replacement (Estimated Construction Time)
- Basement/ First Floor – North and West Corridors (10/1/26 – 3/1/27)
- Second & Third Floor – North and West Corridors (4/1/27 – 10/1/27)
- Basement/ First Floor – South and East Corridors (11/1/27 – 3/1/28)
- Second & Third Floor – South and East Corridors (1/1/28 – 9/1/28)
Shuster Hall |
|||||||
|---|---|---|---|---|---|---|---|
HVAC Upgrades |
|||||||
| Oct-26 | Mar-27 | Apr-27 | Oct-27 | Nov-27 | Jan-28 | Mar-28 | Sept-28 |
| Basement/First Floor - North & West Corridors | |||||||
| Second/Third Floor - North & West Corridors |
|||||||
| Basement/First Floor - South & East Corridors |
|||||||
| Second & Third Floors - South & East Corridors |
|||||||
Leonard Lief Library
Window Replacement (Estimated Construction Time)
- Third Floor (12/7/25 – 1/14/26)
- Second Floor (1/17/26 – 3/13/26)
- First Floor (3/14/26 – 4/25/26)
- Basement (3/14/26 – 4/25/26)
Leonard Lief Library |
||||
|---|---|---|---|---|
Window Replacement |
||||
| Dec-25 | Jan-25 | Feb-25 | April-26 | April-26 |
| Third Floor | ||||
| Second Floor | ||||
| First Floor | ||||
| Basement | ||||
Old Gym Building
Center for Teaching and Learning (Estimated Construction Time)
(Completed by End of '25)
Window Replacement (Estimated Construction Time)
(February '26 – Summer '28)
Old Gym Building |
|||
|---|---|---|---|
Construction Projects |
|||
| Oct-25 | Dec-25 | Feb-26 | Aug-28 |
| Center for Teaching & Learning | |||
| Window Replacement | |||
Gillet Hall
Roof Replacement (Estimated Construction Time)
(9/5/25 – 12/20/25)
Gillet Hall |
||
|---|---|---|
Roof Replacement |
||
| Oct-25 | Nov-25 | Dec-25 |
| Roof Replacement | ||
Carman Hall
Carman Hall Projects
- Plaza Roof Replacement (Complete by November '25)
- West Main Staircase/Entrance Rebuild (Complete by December '25)
- East Main Staircase/Entrance Rebuild (December '25 - June '26)
- Terraces Rebuild (May '26 – August 26)
- Bathroom Accessibility Improvements (November '25 - May '27)
- HVAC Upgrade (June '26 - June -29)
Carman Hall |
||||||||
|---|---|---|---|---|---|---|---|---|
Construction Projects |
||||||||
| Oct-25 | Nov-25 | Dec-25 | May-26 | June-26 | Aug-26 | Nov-26 | May-27 | |
| Plaza Roof | ||||||||
| West Staircase/Entrance | ||||||||
| East Staircase/Entrance | ||||||||
| Terraces | ||||||||
| Bathrooms | ||||||||
| HVAC | ||||||||
Music Building
Facade Work / Copper Roof Refurbishment (Estimated Construction Time)
(7/5/25 – 8/1/26)
Music Building |
||
|---|---|---|
Facade and Roof Repair |
||
| Oct-25 | Jan-26 | August-26 |
| Facade Work | ||
| Copper Roof Refurbishment | ||
Campus Bridge
Structural Restoration (Estimated Construction Time)
(Winter '25 – Winter '26)
Campus Bridge |
||
|---|---|---|
Structural Restoration |
||
| Dec-25 | June-26 | Dec-26 |
| Repair and Restoration | ||
Davis Hall
Roof Replacement (Estimated Construction Time)
(7/5/25 – 8/1/26)
Davis Hall |
||
|---|---|---|
Construction Projects |
||
| Jun-25 | Oct-26 | Dec-25 |
| Roof Replacement | ||
| Social Work Department | ||
-