BUILDING CONSTRUCTION DETAILS


For any questions or concerns please contact the Office of Campus Planning & Facilities at campus.facilities@lehman.cuny.edu or 718-960-8226.

Shuster Hall Library Old Gym Gillet Hall Carman Hall Music Building Campus Bridge Davis Hall


Shuster Hall

Window Replacement (Estimated Construction Time)

UPDATE: Work on the window replacements for Shuster Hall is currently delayed. Restoration work on other exterior elements of Shuster Hall continues. A return date for the third floor is not currently known.

  • Third Floor (10/10/25 – 11/23/25)
  • Basement (Construction Start Delayed)
  • Second Floor (Construction Start Delayed)
  • First Floor (Construction Start Delayed)

Shuster Hall

Window Replacement
Oct-25 Nov-25 Dec-25 Jan-26 Feb-26
Third Floor    
      Basement - Construction Start Delayed
      Second Floor - Construction Start Delayed
      First Floor - Construction Start Delayed

Temporary Office Locations beginning September 29, 2025

HVAC (Air Conditioning) Replacement (Estimated Construction Time)
  • Basement/ First Floor – North and West Corridors (10/1/26 – 3/1/27)
  • Second & Third Floor – North and West Corridors (4/1/27 – 10/1/27)
  • Basement/ First Floor – South and East Corridors (11/1/27 – 3/1/28)
  • Second & Third Floor – South and East Corridors (1/1/28 – 9/1/28)

Shuster Hall

HVAC Upgrades
Oct-26 Mar-27 Apr-27 Oct-27 Nov-27 Jan-28 Mar-28 Sept-28
Basement/First Floor - North & West Corridors            
    Second/Third Floor -
North & West Corridors
       
        Basement/First Floor -
South & East Corridors
 
          Second & Third Floors -
South & East Corridors

Leonard Lief Library

Window Replacement (Estimated Construction Time)
  • Third Floor (12/7/25 – 1/14/26)
  • Second Floor (1/17/26 – 3/13/26)
  • First Floor (3/14/26 – 4/25/26)
  • Basement (3/14/26 – 4/25/26)

Leonard Lief Library

Window Replacement
Dec-25 Jan-25 Feb-25 April-26 April-26
Third Floor      
  Second Floor  
      First Floor
      Basement

Old Gym Building

Center for Teaching and Learning (Estimated Construction Time)

(Completed by End of '25)

Window Replacement (Estimated Construction Time)

(February '26 – Summer '28)

Old Gym Building

Construction Projects
Oct-25 Dec-25 Feb-26 Aug-28
Center for Teaching & Learning  
    Window Replacement

Gillet Hall

Roof Replacement (Estimated Construction Time)

(9/5/25 – 12/20/25)

Gillet Hall

Roof Replacement
Oct-25 Nov-25 Dec-25
Roof Replacement

Carman Hall

Carman Hall Projects
  • Plaza Roof Replacement (Complete by November '25)
  • West Main Staircase/Entrance Rebuild (Complete by December '25)
  • East Main Staircase/Entrance Rebuild (December '25 - June '26)
  • Terraces Rebuild (May '26 – August 26)
  • Bathroom Accessibility Improvements (November '25 - May '27)
  • HVAC Upgrade (June '26 - June -29)

Carman Hall

Construction Projects
Oct-25 Nov-25 Dec-25 May-26 June-26 Aug-26 Nov-26 May-27
Plaza Roof            
West Staircase/Entrance          
    East Staircase/Entrance      
      Terraces    
  Bathrooms
        HVAC

Music Building

Facade Work / Copper Roof Refurbishment (Estimated Construction Time)

(7/5/25 – 8/1/26)

Music Building

Facade and Roof Repair
Oct-25 Jan-26 August-26
Facade Work
Copper Roof Refurbishment

Campus Bridge

Structural Restoration (Estimated Construction Time)

(Winter '25 – Winter '26)

Campus Bridge

Structural Restoration
Dec-25 June-26 Dec-26
Repair and Restoration

Davis Hall

Roof Replacement (Estimated Construction Time)

(7/5/25 – 8/1/26)

Davis Hall

Construction Projects
Jun-25 Oct-26 Dec-25
Roof Replacement
Social Work Department