Thanks to the generosity and commitment to a quality education from our elected officials, Lehman College has embarked on a multi-year plan to renovate and upgrade many of our buildings across campus. This will allow Lehman to continue offering a high-quality education in top-quality spaces.

Among the benefits are:

New Roofs

❏ Better insulated windows

❏ Environmentally efficient air-conditioning and heating

❏ Safer facades and parapets

❏ Improved Accessibility

We are conducting this work as quickly and safely as possible to keep the disruptions to a minimum, but many people will need to temporarily relocate their offices at some point during the next three years until all the work is complete in 2028.

Supervisors in each affected area have been notified and are working out plans for temporary office moves and any changes to in-person requirements for administrators and staff.

See below for a brief description of the work being done on each building, click More Details for further information.

For any questions or concerns please contact the Office of Campus Planning & Facilities at campus.facilities@lehman.cuny.edu or 718-960-8226.

Buildings

Shuster Hall

Projects
UPDATE: Window Replacement (10/25 – 3/26) - This project is currently delayed
HVAC (10/26 – 9/28/)
More Details

Leonard Lief Library

Projects

Window Replacement (12/25 – 4/26)
More Details

Old Gym

Projects
Center for Teaching and Learning (1/25 - 12/25)
Window replacement (2/26 – 8/28)
More Details

Gillet Hall

Projects

Roof Replacement (8/25 – 12/25)
More Details

Carman Hall

Projects
Plaza Roof Replacement (5/25 - 11/25)
West Staircase/Entrance (8/25 – 12/25)
East Staircase/Entrance (12/25 – 6/26)
Terraces (5/26 - 8/27)
Bathroom Accessibility Improvements (11/25 - 5/27)
HVAC Upgrade (6/26 - 6/29)
More Details

Music Building

Projects

Facade Work (6/25 – 8/26)
Copper Roof Maintenance (6/25 - 8/26)
More Details

Campus Bridge

Projects
Structural Restoration (11/25 – 11/26)
More Details

Davis Hall

Projects

Roof Replacement (8/25 – 10/25)
Social Work Department (12/25)
More Details